		 i recieved this last night so i am more relaxed and all my sites are up this is from the DC: 
 
This message is from our data center director: 
 
All possible steps are being taken to ensure the smooth running of   
servers 
during this storm, though it is possible there may be some downtime due  
to 
this natural disaster. 
 
Disaster planning is currently and has been underway for some time. We  
will 
operate our core services with a limited staff so that the bulk of our 
employees can be with their families. A core staff of approximately 25  
will be 
on hand in the DC throughout the storm. This includes a facilities  
specialist 
as well as an a/c specialist. 
 
DC staff will be on hand to handle emergency repairs and tickets.  
Routine 
tickets and upgrades will most probably have a delayed response. 
 
As an extra precaution, we have sourced an additional rental generator.  
While 
this unit would not be needed for a brief outage, if we were to  
experience a 
loss of power lasting several days, we would need to perform normal 
maintenance on our generators, and this would give us a generator to  
run while 
that maintenance is taking place. Maintenance such as oil changes is  
required 
under our operating specifications every 100 to 150 hours, meaning that  
we 
would need to perform maintenance sometime after 4-5 days. All total,  
we have 
in excess of 10,000 gallons of fuel on site. We have guaranteed  
contracts for 
fuel delivery and two fuel depots are located within 2 miles of our  
facility. 
 
We anticipate that the coming storm will have no impact on our  
operations. 
However, we are prepared to deal with any eventuality. 
 
Our buildings are designed to withstand Cat 4 conditions. It would be a  
highly 
improbable situation for us to sustain a cat 4 this far inland. It is 
anticipated that we will see high Cat 3 conditions .... based upon the  
current 
track and our location. 
 
All our providers have disaster and contingency plans and we are in  
contact with 
them ensuring that our mutual emergency contacts. 
 
Due to evacuations and limited staff, ticket responses will likely slow  
during 
this situation. No upgrades will take place until we restore complete 
operations. New server purchases will be limited to that on hand and no  
new 
servers will be placed into service. 
 
Thank you for your understanding. 
 
 
so i am pretty sure i am ok will see later tonight--looks like they have plenty of fuel, seems strange we have tons of fuel for porn but all the people on the highway are stranded and have none ??? what a world 
		
	
		
		
		
		
		
		
			
		
		
		
		
		
		
	
	 |